***Airfield Closures*** Please monitor NOTAMs for the most up to date closure information


About the 2024 Runway Reconstruction Project:

The TxDOT-managed 2024 Runway Reconstruction Project will be a full reconstruction of the 18L-36R runway at Denton Enterprise Airport.  The project will correct significant subgrade and line of sight issues with a full-depth repair of approximately 1,200 feet of runway pavement. The effort will also include the reconstruction of several taxiway stubs, construction of a new A6 taxiway, and the installation of LED runway lights and PAPIs.

 

The project will follow a multi-phase schedule, beginning in April 2024. Phase I will include a short closure of the runway to install a temporary Alpha 6 connector. Phase II will start thereafter which will result in the southern end of the runway being closed for reconstruction. Phase III, anticipated to begin in July 2024, will result in the full runway closure for approximately 45 days to complete the remaining portions of the runway. The remaining phasing will include runway lighting and PAPI installation during nighttime closures.


PHASE I CLOSURES


Monday April 1, 2024

Runway 18L‐36R (Main Runway) will be closed to takeoffs and landings

beginning at 8:00am. Taxiway Alpha South of A6 will be closed beginning at 8:00am.


Tuesday April 2, 2024

Runway 18L‐36R (Main Runway) will remain Closed. Taxiway Alpha South of A6 will remain closed. Runway 18R‐36L (West Runway) will be closed beginning at 9:00pm.


Wednesday April 3, 2024

Runway 18R‐36L (West Runway) will be reopened Full length at 7:00am.

Taxiway Alpha South of A6 will remain closed. Runway 18L‐36R (Main Runway) will be reopened at 7:00am with the following declared distances until the completion of the project phase.